PROJECT AUTHORIZATION |
PACKET ID: PMT-RK0E |
CONTRACT ID |
EMARS PROGRAM CODE |
AUTHORIZATION NO: |
|
1549001D |
15490 |
0 |
It is hereby ordered that the project herein described be undertaken and accomplished within the funding level authorized. |
PROJECT ID |
PROJECT ID NUMBER |
FEDERAL PROJECT NUMBER |
6 YR PLAN ITEM NUMBER |
6 YR PLAN ITEM PARENT NUMBER |
|
|
|
11-80253 |
|
PROJECT TYPE |
PROJECT LENGTH |
NUMBER OF BRIDGES |
SYSTEMS |
PAVE RECON W/ALIGN |
1.5290 MI |
|
|
PROJECT PHASE
&
RESPONSIBILITY |
PLANNING |
DESIGN |
RIGHT OF WAY |
UTILITIES |
|
CONSULT |
|
|
CONSTRUCTION |
TITLE DEEDED TO: |
MAINTENANCE |
OTHER |
|
|
|
|
FUNDING & TIME
ACCOUNTABILITY |
PARTICIPATING AGENCIES |
FEDERAL |
|
STATE |
DOH |
LOCAL |
|
OTHER |
|
REQUESTED FUNDS FOR THIS AUTHORIZATION
ITEM NUMBER |
PHASE |
FUND |
PROGRAM |
FEDERAL FISCAL YEAR |
STATE FISCAL YEAR
|
FEDERAL APPR
CODE |
CURRENT FUNDING REQUEST |
11-80253 |
D |
1100 |
FD04 |
|
2023 |
|
$1,300,000.00 |
CURRENT FUNDING REQUEST TOTAL: $1,300,000.00 |
AUTHORIZATION SUMMARY FOR THIS 10-1 SERIES |
PHASE |
TOTAL AUTHORIZATION TO DATE (INCL. CURRENT REQUEST) |
PLANNING |
$0.00 |
DESIGN |
$1,300,000.00 |
UTILITIES |
$0.00 |
R/W |
$0.00 |
CONSTRUCTION |
$0.00 |
NON-HIGHWAYS |
$0.00 |
|
Total: $1,300,000.00 |
THIS AUTHORIZATION PROVIDES FD04 FUNDS FOR DESIGN. |
|
Project Approval Recommended By:
James Ballinger 8/3/2022 |
Signed and Approved by:
Jim Gray 8/3/2022 |
ITEM NO. |
COUNTY |
DIST |
FACILITY NAME
|
ROUTE |
LENGTH |
11-80253.00 |
CLAY
|
11 |
KY-3472 BEECH CREEK RD |
KY 3472 |
1.5290 MI |
IMPROVE GEOMETRIC ALIGNMENT FROM KY 3472 AT MP 1.7 CONTINUING PAST THE BERT. T. COMBS PARK TO THE INTERSECTION OF BEECH CREEK ROAD AND WHITE OAK ROAD. (APPROXIMATELY 1.5 MILES OF ROADWAY TO IMPROVE) (2022CCN) |